Retail Center at Greenhouse Rd
Project Timeline

Steel is now going up as we enter another major phase of construction. The retail center is taking shape faster with every milestone achieved.
Metal structure work has begun, and the transformation continues.
A major construction milestone has been achieved with the completion of over 20,000 CMU blocks.
Over 20,000 CMU blocks are rapidly taking shape as the retail center site begins its vertical transformation.

500 yards of concrete poured successfully.

500 yards of Rebar Tied in Preparation for the concrete pour.
Another major overnight concrete pour completed — 600 yards down, more progress ahead.
CMU installation is underway with 20,000 blocks across 2,000 yards.
Another round of over 400 yards of concrete poured.
Within a week, another 350+ yards poured overnight
Over 600 yards of concrete poured overnight with more than 40 Stealth crew.
Prep for concrete pour is underway.
The utilities phase is in progress, with piping installation.
Site clearing is complete and the project is now moving into the underground utilities phase.